15M €

LOCATION

Région Aquitaine, France

SURFACE

38000m2

The objective for the group’s general management is to formalise the state of play of production capacities, anticipate demand and budget investments to adapt industrial tools to 3, 5 and 10 years

First, we provided an overview of the following points :

  • Functional distribution
  • Surface planning
  • Macro flows
  • Production capacity
  • Expansion potential
  • HSE
  • Qualitative

Then we provide elements to anticipate the needs of the site in the coming years through :

  • A study on quantitative and qualitative needs
  • The modelling of production and packaging capacity
  • The identification of bottlenecks on the basis of a shared inventory, validated with growth assumptions