PLAN
Master plan
Feasability study
Pre-project
Specification draftings and suppliers consultations
Managing Implementationn
Master plan
Feasability study
Pre-project
Specification draftings and suppliers consultations
Managing
Implementation
Implementation
INVESTMENT
15M €
LOCATION
Région Aquitaine, France
SURFACE
38000m2
The objective for the group’s general management is to formalise the state of play of production capacities, anticipate demand and budget investments to adapt industrial tools to 3, 5 and 10 years
First, we provided an overview of the following points :
- Functional distribution
- Surface planning
- Macro flows
- Production capacity
- Expansion potential
- HSE
- Qualitative
Then we provide elements to anticipate the needs of the site in the coming years through :
- A study on quantitative and qualitative needs
- The modelling of production and packaging capacity
- The identification of bottlenecks on the basis of a shared inventory, validated with growth assumptions
- The creation of potential development scenarios for the site

